A Multi-Objective Decision-Making Framework for Optimizing Resource Allocation, Project Scheduling, and Financial Performance in Repetitive Construction Projects

Authors

  • Yasser Aboelmagd Vice Dean, College of Engineering, University of Business & Technology (UBT), Jeddah, Saudi Arabia
  • Remon Eskander Mathematics and Physics Engineering Department, Faculty of Engineering, Alexandria University, Egypt.
  • Omnia Darwish Engineering Programs Director, Field of Engineering, Alamein International University (AIU), New Al-Alamein City, Matrouh - Egypt.

Keywords:

Mega Construction, Repetitive Projects, Multi-Resources, Multi-Objective Optimization, Optimizing Strategy, Scheduling Software, Tender Data Estimation.

Abstract

Accurate forecasting of critical tender parameters, including anticipated project duration, total gross valuation and cash flow patterns, constitutes a fundamental yet demanding responsibility for contractors operating within the highly competitive construction sector. Given the persistent need to reconcile constrained profit margins with efficient project delivery, this study presents Optimizing Strategy Software (OSS), a Java-based, multi-objective optimisation framework developed specifically for repetitive construction projects characterised by uniform activity durations and single-crew assignments. Rather than relying exclusively on conventional estimation approaches, OSS systematically examines alternative multi-mode resource configurations to identify technically feasible and economically advantageous project execution scenarios. Its principal purpose is to provide practical, scenario-oriented decision support through which project managers can optimise resource allocation while concurrently reducing total project duration, final tender price and peak working capital requirements, alongside maximising net present value (NPV). To ensure compatibility with established computational project management environments, the software incorporates a four-tier architecture consisting of a user interface module, a centralised relational database module, a computational execution module and a dynamic connecting module. The proposed theoretical formulation and computational functionality are subsequently examined through a detailed illustrative case study involving a large-scale repetitive expressway construction project. The application demonstrates the effectiveness of OSS in identifying favourable resource allocation strategies and improving the optimisation of interrelated tender parameters, thereby establishing its practical relevance as an integrated decision-support framework for repetitive construction planning.

Downloads

Download data is not yet available.

References

[1] Nguyen, D. A., Nguyen, N.-T., Tran, Q., & Tran, D.-H. (2023). Tradeoff different construction project goals in using a novel multi-objective sea horse algorithm. Alexandria Engineering Journal, 82, 55-68. https://doi.org/10.1016/j.aej.2023.09.059

[2] Kumar, K. M., Agrawal, D., Vishwakarma, V. K., & Eirgash, M. A. (2024). Development of time-cost trade-off optimization model for indian highway construction projects using non-dominated sorting genetic algorithm-II methodology. Asian Journal of Civil Engineering, 25(8), 5975-5988. https://doi.org/10.1007/s42107-024-01157-y

[3] Alhijawi, B., & Awajan, A. (2024). Genetic algorithms: Theory, genetic operators, solutions, and applications. Evolutionary Intelligence, 17(3), 1245-1256. https://doi.org/10.1007/s12065-023-00822-6

[4] Ghoroqi, M., Ghoddousi, P., Makui, A., Shirzadi Javid, A. A., & Talebi, S. (2024). Integration of resource supply management and scheduling of construction projects using multi-objective whale optimization algorithm and NSGA-II. Soft Computing, 28(11-12), 6983-7001. https://doi.org/10.1007/s00500-023-09467-0

[5] Aziz, R. F. (2013). Optimizing strategy for repetitive construction projects within multi-mode resources. Alexandria Engineering Journal, 52(1), 67-81. https://doi.org/10.1016/j.aej.2012.11.003

[6] Abdelbasset, E., Hassan, A., Amer, N. H., & Khalifa, Y. A. (2023). Optimizing the number of crews working in parallel and their work sequence to minimize project duration and cost for repetitive construction projects. Innovative Infrastructure Solutions, 8(11), 288. https://doi.org/10.1007/s41062-023-01233-3

[7] Altuwaim, A., Alagha, E., Mahmoud, A. B., & Saad, D. A. (2024). Adaptive LOB scheduling for optimizing resource leveling and consumption. JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 30(3), 220-233. https://doi.org/10.3846/jcem.2024.20952

[8] Iranagh, M., Sonmez, R., Atan, T., Uysal, F., & Bettemir, Ö. H. (2023). A memetic algorithm for the solution of the resource leveling problem. Buildings, 13(11), 2738. https://doi.org/10.3390/buildings13112738

[9] Lazari, V., Chassiakos, A., & Karatzas, S. (2024). Multi-objective resource-constrained scheduling in large and repetitive construction projects. Algorithms, 17(8), 351. https://doi.org/10.3390/a17080351

[10] Jia, T. (2025). Optimizing construction project plan management using parameter-adaptive improved genetic algorithm. Tehnički vjesnik, 32(1), 98-106. https://doi.org/10.17559/TV-20240720001868

[11] Peng, J., Feng, Y., Zhang, Q., & Liu, X. (2023). Multi-objective integrated optimization study of prefabricated building projects introducing sustainable levels. Scientific Reports, 13(1). https://doi.org/10.1038/s41598-023-29881-6

[12] Yang, C. (2024). Construction scheduling optimization in the prefabricated buildings through multi-objective GA on the principle of sustainable development. Archives of Civil Engineering, 70(3), 459-472. https://doi.org/10.24425/ace.2024.150995

[13] Hassan, A., El-Rayes, K., & Attalla, M. (2023). Stochastic scheduling optimization of repetitive construction projects to minimize project duration and cost. International Journal of Construction Management, 23(9), 1447-1456. https://doi.org/10.1080/15623599.2021.1975078

[14] Albayrak, G. (2024). Metaheuristic multi-objective optimization approach for repetitive construction project scheduling. Adıyaman Üniversitesi Mühendislik Bilimleri Dergisi, 11(24), 438-454. https://doi.org/10.54365/adyumbd.1477358

[15] Hasan, M. F., & Mohammed, S. R. (2022). Time and finance optimization model for multiple construction projects using genetic algorithm. Journal of the Mechanical Behavior of Materials, 31(1), 267-281. https://doi.org/10.1515/jmbm-2022-0032

[16] Wu, Z., & Ma, G. (2023). Automatic generation of BIM-based construction schedule: Combining an ontology constraint rule and a genetic algorithm. Engineering, Construction and Architectural Management, 30(10), 5253-5279. https://doi.org/10.1108/ecam-12-2021-1105

[17] Essam, N., Khodeir, L., & Fathy, F. (2023). Approaches for BIM-based multi-objective optimization in construction scheduling. Ain Shams Engineering Journal, 14(6), 102114. https://doi.org/10.1016/j.asej.2023.102114

[18] Zhang, Y. (2025). Development of an integrated intelligent BIM-based model for multi-objective optimization in engineering assembly processes. PLOS One, 20(11), e0333354. https://doi.org/10.1371/journal.pone.0333354

[19] Yao, Y., Tam, V. W. Y., Wang, J., Le, K. N., & Butera, A. (2024). Automated construction scheduling using deep reinforcement learning with valid action sampling. Automation in Construction, 166, 105622. https://doi.org/10.1016/j.autcon.2024.105622

[20] Soleymani, M., Bonyani, M., & Wang, C. (2024). Simulation of autonomous resource allocation through deep reinforcement learning-based portfolio-project integration. Automation in Construction, 162, 105381. https://doi.org/10.1016/j.autcon.2024.105381

[21] Prieto, S. A., Mengiste, E. T., & García de Soto, B. (2023). Investigating the use of ChatGPT for the scheduling of construction projects. Buildings, 13(4), 857. https://doi.org/10.3390/buildings13040857

[22] Al-Refaie, A., Al-Hawadi, A., Lepkova, N., & Abbasi, G. (2023). Blockchain of optimal multiple construction projects planning under probabilistic arrival and stochastic durations. Journal of Civil Engineering and Management, 29(1), 15-34. https://doi.org/10.3846/jcem.2023.17927

Downloads

Published

2026-06-30

How to Cite

Yasser Aboelmagd, Remon Eskander, & Omnia Darwish. (2026). A Multi-Objective Decision-Making Framework for Optimizing Resource Allocation, Project Scheduling, and Financial Performance in Repetitive Construction Projects. Decision Making: Applications in Management and Engineering, 9(1), 714–737. Retrieved from https://www.dmame-journal.org/index.php/dmame/article/view/1895